Is it too late to get my job done before the family dinner?

Maybe not, depending on what you have done. If we are only talking about replacing Formica tops with granite tops and maybe new appliances then there is still time to get the work done. A full kitchen remodel with complete tear out and replacement of absolutely everything normally will take at least four weeks. Of course actual down time for the kitchen would be just the last week of the four, as the first three weeks are for ordering, building cabinets, cutting granite and so forth.